| Our Projects | 
           
           
            |   | 
           
           
             | 
           
           
            |   | 
           
           
             
                 
                  | No | 
                  Description | 
                  Contract Value | 
                  Year of Completion | 
                 
                 
                  | 1 | 
                  Upgrading of 4 pumping stations including 
                      surge analysis, sump model tests and ancillary equipment  | 
                  S$2,755,100 | 
                  1997/1998 | 
                 
                 
                  | 2 | 
                  Kim Chuan STW - 6 sets DAFT (Dissolved Air 
                      Flotation Thickeners) capacity 360m3 /hour 
                      Main Contractor: Dayen Environmental Ltd 
                      Owner: Public Utilities Board, Singapore  | 
                  S$2,053,600 | 
                  Dec 2001 | 
                 
                 
                  | 3 | 
                  M&E Works at Sentosa Cove - Various pumping 
                      stations 
                      Main Contractor: Lee Hong Construction 
                      Owner: Sentosa Development Corporation  | 
                  S$679,365 | 
                  Dec 2001 | 
                 
                 
                  | 4 | 
                  Design, Supply, Installation & Commissioning 
                      of Polymer Make-Up System at Chestnut Ave & Choa Chu Kang 
                      Waterworks. Polymer is used as an aid in thickening and dewatering 
                      process in the treatment plants 
                      Main Contractor: Salcon Ltd 
                      Owner: Public Utilities Board, Singapore  | 
                  S$926,388 | 
                  Jan 2002 | 
                 
                 
                  | 5 | 
                  Design, fabricate, supply 10 sets of Polymer 
                      Make-Up systems at Ulu Pandan Water Reclamation Plant - The 
                      preparation system are to facilitate thickening and dewatering 
                      process 
                      Main Contractor: Sembcorp E & C 
                      Owner: Public Utilities Board, Singapore   | 
                  S$993,720 | 
                  Nov 2001 | 
                 
                 
                  | 6 | 
                  Upgrading of M&E Equipment at Paya Lebar 
                      Pumping Station - One of the biggest pumping station in Singapore. 
                      There are 5 pumps each 700L/S capacity with HT 6.6KV motor 
                      of 450KW. Each disintegrator has capacity of 1511L/S. The 
                      works also include surge suppression system, vibration studies 
                      and monitoring system, sump model test. 
                      Owner: Public Utilities Board, Singapore  | 
                  S$3,290,000 | 
                  Feb 2002 | 
                 
                 
                  | 7 | 
                  Supply & Installation of Air-Cooled Condenser 
                      Fans at Tuas Incineratin Plant - ENV 
                      Owner: Tuas Incineration Plant  | 
                  S$728,000 | 
                  Nov 2001 | 
                 
                 
                  | 8 | 
                  Supply and installation of 4 nos. Silo Bins 
                      each 500m3 ca pacities at Seletar STW - The design 
                      and construction of these sludge storage facilities are to 
                      receive the dewatered sludge before disposal or incineration 
                      Main Contractor: Hyundai E&C 
                      Owner: Public Utilities Board, Singapore  | 
                  S$640,000 | 
                  Aug 2002 | 
                 
                 
                  | 9 | 
                  Phasing out of STPS at Lornie Road/Adam Drive 
                      in Marina Basin Catchment - Ah Boon Civil Engineering & 
                      Bldg Contractors Pte Ltd 
                      Owner: Public Utilities Board, Singapore  | 
                  S$190,000 | 
                  Jul 2001 | 
                 
                 
                  | 10 | 
                  Design, supply and installation of Dewatered 
                      Conveyor System at Bedok STW - Dayen Engineering Pte Ltd 
                      Owner: Public Utilities Board, Singapore  | 
                  S$172,000 | 
                  Dec 2001 | 
                 
                 
                  | 11 | 
                  Supply, installation, testing and commissioning 
                      of Mechanical Ventilation systems at Loyang 
                      Main Contractor: Deltafield Holding Pte Ltd 
                      Owner: Public Utilities Board, Singapore  | 
                  S$350,000 | 
                  Feb 2003 | 
                 
                 
                  | 12 | 
                  Design, Fabricate, install and painting of 
                      2 nos. silo bins each 250m3 capacities at Kim Chuan 
                      STW 
                      Main Contractor: Dayen Environmental Ltd 
                      Owner: Public Utilities Board, Singapore  | 
                  S$350,000 | 
                  Nov 2002 | 
                 
                 
                  | 13 | 
                  Upgradig of Holland Road Pumping Station - 
                      Design, supply, install, test and commissioning M&E Equipment 
                      in the pumping station  
                      Owner: Public Utilities Board, Singapore  | 
                  S$2,878,339 | 
                  Mar 2005 | 
                 
                 
                  | 14 | 
                  Jurong WRP Contract 4 - Design and build 2 
                      set DAFT, Polymer Preparation System 
                      Main Contractor: Dayen Environmental Ltd 
                      Owner: Public Utilities Board, Singapore  | 
                  S$1,155,000 | 
                  May 2004 | 
                 
                 
                  | 15  | 
                  Pumping Station Tembusu Ave, Jurong Islang 
                      Mechanical & Electrical Equipment 
                      Main Contractor: Planar One Associates P/L 
                      Owner: Jurong Town Corporation  | 
                  S$1,652,134 | 
                  Dec 2005 | 
                 
                 
                  | 16 | 
                  Upgrading of Pepys Pumping Station 
                      Owner: Public Utilities Board, Singapore   | 
                  S$1,313,000 | 
                  Dec 2003 | 
                 
                 
                  | 17 | 
                  Design, supply, install, test and commission 
                      M&E Equipment at Tengah Pumping 
                      Owner: Public Utilities Board, Singapore   | 
                  S$966,000 | 
                    | 
                 
                 
                  | 18 | 
                  Polymer Preparation System at Port Dickson 
                      Lancang (Melaka), Hilir Perak (Perak)  | 
                  S$300,000 | 
                  Sep 2003 | 
                 
                 
                  | 19 | 
                  Jurong WRP Contract 3 - Design, build 20m 
                      diameter vertical raised Gas holder with gas storage capacity 
                      3,400m3. The methane gas is produced from anaerobic 
                      digester andstored in gas holder. The gas from gas holder 
                      is used to fuel the dual fuel generators which power the treatment 
                      plant 
                      Main Contractor: Sembcorp Engineers and Constructors Ltd 
                      Owner: Public Utilities Board, Singapore   | 
                  S$483,000 | 
                  Apr 2004 | 
                 
                 
                  | 20 | 
                  Supply of 2 sets Polymer Preparation System 
                      at Sungai Semenyih - The design of the polymer preparation 
                      with bulk storage capacity is used in the sludge dewatering 
                      facilities of the water treatment plant 
                      Main Contractor: Chemical Waste Management, Malaysia  | 
                  S$145,000 | 
                  May 2004 | 
                 
                 
                  | 21 | 
                  Upgrading Pulau Saigon Pumping Station - The 
                      works comprise of design, supply, install, test and commission 
                      plant equipment, electrical switchboard, surge suppression 
                      system, vibration studies and monitoring sump model tests 
                      Owner: Public Utilities Board, Singapore   | 
                  S$1,996,000 | 
                  Jan 2004 | 
                 
                 
                  22   | 
                  Kim Chuan WRP - Design and build 12 nos. Primary 
                      and Final Clarifiers and other M&E Works in the waster 
                      water treatment. 8 nos. primary clarification facilities and 
                      4 nos. final clarifications before being sent to dissolved 
                      air flotation thickeners (DAFT) for thickening. The sludge 
                      from DAFT is sent to digester and part as Returned Activated 
                      Sludge (RAS) 
                      Owner: Public Utilities Board, Singapore   | 
                  S$2,537,380 | 
                  Dec 2004 | 
                 
                 
                  | 23 | 
                  NEWater Pipeline and in-line Booster pump 
                      Facility to serve Loyang and Changi North Areas 
                      Owner: Public Utilities Board, Singapore   | 
                  S$590,800 | 
                  Dec 2005 | 
                 
                 
                  | 24 | 
                  Improveent Works at Bedok WRP - Ah Boon Civil 
                      Engineering & Bldg Contractors Pte Ltd 
                      Owner: Public Utilities Board, Singapore  | 
                  S$306,000 | 
                  Jul 2005 | 
                 
                 
                  | 25 | 
                  Upgrading of Tanjong Penjuru Pumping Station 
                      - The works includes pumps screens, hydraulic operated inlet 
                      penstocks, valves, electric hoists, designing ventilation 
                      system & odour control system, surge analysis and sump 
                      model test 
                      Owner: Public Utilities Board, Singapore   | 
                  S$1,054,000 | 
                  Jan 2006 | 
                 
                 
                  | 26 | 
                  Upgrading of Penjuru Pumping Station - The 
                      works comprise of construction of new electrical substation, 
                      the design, manufacture, supply, installl, test and commission 
                      plant equipment including surge suppression measures, vibration 
                      studies, vibration monitoring and sump model test 
                      Owner: Public Utilities Board, Singapore   | 
                  S$1,854,000 | 
                  Feb 2006 | 
                 
                 
                  | 27 | 
                  Sungei Kinta - 2 Sets Polymer and 2 sets Fluoride 
                      Preparation System. 
                      Main Contractor: Salcon Engineering S/B  | 
                  S$155,300 | 
                  Jan 2005 | 
                 
                 
                  | 28 | 
                  Replacement of Ejector system, drainage pump 
                      and vertical turbine pump at Singapore Changi Airport 
                      Owner: Civil Aviation Authority of Singapore  | 
                  S$128,000 | 
                  Nov 2006 | 
                 
                 
                  | 29 | 
                  Design, and Build Lime Preparation and Dosing 
                      for Ulu Pandan Newater Factory - This is a fast track contract 
                      of 5 months including civil works. this plant is capable of 
                      handling the lime dosing of 146 millions litres per day capacity. 
                      The Newater plant belongs to Keppel Seghers Engineering  | 
                  S$2,182,000 | 
                  Feb 2007 | 
                 
                 
                  | 30 | 
                  Effluent storage tank at Kranji Newater Factory 
                      - The works also involve underground pipe laying  | 
                  S$478,000 | 
                  May 2007 | 
                 
                 
                  | 31 | 
                  Keppel Marina Pumping Station - Design new 
                      pumping station including equipment, surge suppression system, 
                      vibration studies and monitoring system.  | 
                  S$660,000 | 
                  Jun 2007 | 
                 
                 
                  | 32 | 
                  Design, supply, installation, testing & 
                      commissioning of an Industrial Water Tank and Pumping Facility 
                      at Terminal 2, Singapore Changi Airport  | 
                  S$450,000 | 
                  Apr 2008 | 
                 
                 
                  | 33 | 
                  Proposed Greasy Waste Receiving Facilities 
                      at Jurong WRP   | 
                  S$1,980,000 | 
                  Apr 2008 | 
                 
                 
                  | 34 | 
                  Proposed Odour Treatment Plant to Existing 
                      Sewage Pumping Stations for North Sentosa Cove  | 
                  S$1,025,000 | 
                  Apr 2008 | 
                 
                 
                  | 35 | 
                  Proposed Gateway Avenue Roadwork for Resorts 
                      World at Sentosa  | 
                  S$3,175,568 | 
                  Jun 2008 | 
                 
                 
                  | 36 | 
                  Sewer Rehabilitation in Various Pumping Stations 
                      catchments - Contract 8  | 
                  S$8,583,110 | 
                  Jan 2009 | 
                 
                 
                  | 37 | 
                  Proposed Punggol Reservoir: Dams, Gates, Dredging 
                      and Ancillary Works, Contract 1  | 
                  S$1,421,000 | 
                  Apr 2009 | 
                 
                 
                  | 38 | 
                  Construction of an Abstraction Pond and ancillary 
                      facilities at Gambas Avenue  | 
                  S$1,350,000 | 
                  Sep 2009 | 
                 
                 
                  | 39 | 
                  Westech Mixing Equipment at Bunus & Pantai 
                      - Malaysia 
                      Main Contractor: Hitachi Plant  | 
                  US$1,240,000 | 
                  Dec 2005 | 
                 
                 
                  | 40 | 
                  Supply of Grit Basin Equipment at C3C 
                      Owner: Public Utilities Board, Singapore   | 
                  US$248,400 | 
                  Sep 2005 | 
                 
                 
                  | 41 | 
                  Construction of STW, Phase 1, Package 3 - 
                      Kuala Sawah, Damasara and Sunggala, Malaysia - Design, supply, 
                      installation, testing and commissioning of 8 set WesTech clarifiers, 
                      2 sets Grit Removal Equipment and 20 sets of Polymer Feeder  | 
                  US$1,358,600 
                    RM$1,172,000  | 
                  May 2008 | 
                 
                | 
           
          |